New Dining Hall Project
Timber Ridge camp is an effective ministry of Trout and although God uses this place to change the lives of teenagers, we face a major challenge. The kitchen facility, which is temporary, is vastly undersized at 12’ by 14'. Our food service department cannot cook 175 meals three times a day for an extended period at Timber Ridge so now is our time to respond. Let’s do this together.
› More Ministry
› More Scholarships
› Letter From The President
› Frequently Asked Questions
Ministry to kids and teens at Trout is exciting and ever since we opened Timber Ridge for summer camp, God has blessed campers and staff members with full camps and significant spiritual decisions being made. The challenge before us is Timber Ridge, or TR as our summer staff would say, cannot continue to grow because of a facility limitation.
The bottom line is we are cooking three meals a day out of a kitchen like you have at home (12’ by 14’) for 175 campers. We cannot do this long term and therefore, we are developing a plan to address this TR kitchen limitation. Please pray for God’s wisdom and discernment as we continue to expand.
Spray Insulation Is Applied

The crew is finishing the insulation on the vaulted ceilings so that the emergency fire doors can be installed next week. Also, a volunteer team will help prepare the in-floor heating system in the basement. The plan is to have the in-floor heating installed next week so that the lower floor, which is cement, can be poured. If you haven't seen this building, you should definitely see it first-hand. It will be a great place for ministry.
Kitchen Floor Poured
The dining hall has been enclosed for the winter which means our electricians and sound techs can pull the wiring in a warm building. The first layer of insulation has been sprayed and interior walls are being erected. Also, the cement floor in the kitchen has been poured. Mark and Al are busy building the stairs so that workers can access all three levels of the dining hall.
Windows Installed

This week the construction at Timber Ridge has been fast and furious. We have the roofers here, the windows were installed, the application of the cultured stone is almost complete, volunteers from Berean are working on the electrical and the 248' well was dug. Check out the new Kolbe windows.
Metal Roof Installation

It has been a busy week at Timber Ridge. Our plumbers and volunteers are working on trenching in the pipes for the kitchen and our block layer, Doug Carlson, has been working on the side fireplace. Unfortunately, the weather has been cool and rainy which has delayed the installation of the roof. The roofers will return next week to complete the installation.
Fireplace Stone Work

The areas above the roofline on the fireplaces have the stone work completed. We are now waiting for the windows and roof material to arrive. Our goal is to have the building enclosed before the snow flies. Also, many volunteers made it possible for the sidewalks to be poured this Saturday. The cement will be placed around the exterior of the building.
Dining Hall Trusses are Up

The trusses are up on the new dining hall and the sheeting is being applied. It is an amazing view from the top of the hill at Timber Ridge and we are pleased with the progress that is being made.
Meet Our New Volunteer - Karen

Karen was surfing her home church’s web site and clicked the link to Trout Lake Camps. She noticed on our web site that we are in the process of constructing a new dining hall. Since she had several weeks off of work, she called Mark Grindahl, our Maintenance Director who coordinates volunteers, and volunteered over two weeks of her time.
The great news about Karen is she is a “heavy equipment operator” and is helping us out in a major way. Her skills with heavy equipment help reduce the total cost of the project as well as speed up the construction timeline.
Thanks Karen for your hard work!
Main Fireplace is Being Built

Volunteers and workers are building the main fire place which sits between the serving area and main dining area. The structure is massive (approximately 20' long and over 30' tall). It will take about 5 days to complete the structure and will be finished after the roof is constructed. Thanks for helping make this project possible.
Prestressed Concrete Floors Installed

This week a 120-ton crane with a 167' beam is installing the prestressed concrete floor. The prestressed concrete floor is 8" thick and varies in length (up to 24' long). This portion of the project takes three days to complete and when it is complete the center fireplace structure will be erected. These are exciting days at Timber Ridge.
Foundation is In
This past week the foundation was backfilled and we are preparing to pour the cement on the lower level. This work has been completed by numerous volunteers and some paid sub-contractors. Mark Grindahl is doing a great job managing the project as he works with our architects, state and county regulators, sub-contractors and the numerous volunteers who offer their time to Trout.
It is wonderful to see the progress on the new dining hall and thanks for all your support financially and through volunteer help.
Concrete Block Walls Are Up

This week the concrete block walls are being put into place. Doug, Marty and others are helping lay the foundation. The project is well underway and it is exciting to see progress.
Breaking Ground

Kenny Elg and Mark Grindahl are marking out the location of the new dining hall at Timber Ridge. This building will seat 280 guests with over 10,060 square feet on the main floor. Over the next several weeks the dirt is going to be flying and the foundations will be poured. These are exciting days at Trout Lake Camps.






